INITIATION
In order to meet the required electricity consumption for the initiation step, LNG (Liquefied Natural Gas) driven Power Plant with 12 MW total installed capacity, consisting of 4 units with 2+2+4+4MW configuration, will be erected.
To maintain the security of electricity supply and peak demand supply, 40 MVA switchyard will be installed, and with a substation unit, the industrial park will be connected to the national transmission grid at 132kV voltage level.
DEVELOPMENT
Due to boosted electricity demand following the deployment of new factories in the industrial park, an additional 12 MW installed capacity power plant is planned which extends the total capacity up to 24 MW.
BALANCING
According to energy consumption trend of whole planned factories in operation in the industrial park, final installed capacity will be determined and ultimate power plant configuration will be finalized with additional generation units